DESIGNING SOLUTIONS FOR NOW THAT ARE READY TO SHAPE THE FUTURE. THIS IS NEXXIS.
HomeKnowledge Centre

Water Level Control in a Hydro Power Plant

 

Easy-Laser were called out to a measurement and alignment job in Northern Sweden recently.  Using the Dual Detector, Point Laser, E710 system – this is how the job unfolded.

A large, well renowned, construction company had won a contract to build a gate for water level control in a hydro power plant project. The dam was placed upstream from a hydro power station. The two gates (or valves) were approximately 8.5m x 5 m. Each valve was specified to allow a leakage of 0.2 liters/minute in closed position. This off course meant a very tight seal, and a requirement of high precision alignment on the hinges.

Gate opening.

Traditionally the construction company had been using a total station on a job like this, using it to determine the geometry of the hole construction. There was a problem though, they could not use the total station for the gate hinge alignment.

Easy-Laser were contracted to do the alignment measurement and to provide training in the E710 alignment system on site for the construction workers.

Weather conditions were perfect.

Upon arrival we found two shaft ends pointing at each other. To allow for a good seal these two ends had to be aligned with high precision as the sealing surface is within 10 mm on the sides and 20 mm on the bottom of the gate. To solve this alignment, we had to think of the alignment of these shaft ends as an uncoupled, horizontal shaft alignment.

Shaft end (hinge).

We started off with a rough alignment. Using the dual lasers coning technique, finding rotational center, we saved a lot of time.

A sliding bracket was used as the shaft end were non rotatable.

In order to pick which shaft end to designate as the stationary one we used the E290, digital precision level, to check which one was closest to level.

Ransarn 2

The E290 will connect to either the E710 display box, or a convenient iOS app to display level reading.

The shaft ends were checked for parallelism against the sealing surface using the measuring units in the E710 system and checking straightness over six meters.

The square marks on the shaft surface are used to pinpoint the position of the mag blocks used for the straightness measurement.

Once the shafts had been measured and adjusted the construction crew poured concrete around the shafts to lock them into position. After allowing everything to set for two weeks the gates were mounted without a hinge (pun intended).

A special point of pride for us here at Easy-Laser is that all these measurements were done with an Easy-Laser® E710 alignment system combined with the E290 digital precision level.

Keep in mind that the E290 comes in handy in all on site installation work. With it you can make sure the foundation is flat to within 0.1 mm/m as specified by most manufacturers.

At Easy-Laser we have made it our mission to help the industry achieve optimal running conditions for their machines.

Straightforward by all measures!

 

*This article was originally created by Easy-Laser Tech Jan Oscander,

Join our mailing list // Discover a world of forward-looking solutions designed to shape the future. Ready?